M23 Full Planned Closures Northbound
M23 Resurfacing
I am writing to advise that A-one+ on behalf of Highways England will be carrying out resurfacing Northbound on the M23 between junctions 10 (Copthorne) and 9 (Gatwick)
|
|
In order to carry out these works as efficiently and as safely as possible, work will be undertaken whilst we facilitate 4 FULL weekend closures of the London bound carriageway on the M23, between 10pm on Friday evening to 4am on Monday morning.
These weekend closures are unavoidable due to the nature and scale of the work involved.
| Series of full closures on main carriageway | Dates and timings |
| M23 Junction 10 to Junction 9 London Bound | Friday 12 January 10pm – morning of Monday 15 Jan 4am
Friday 19 January 10pm – morning of Monday 22 Jan 4am Friday 26 Jan 10pm – morning of Monday 29 Jan 4am Friday 2 Feb 10pm – morning of Monday 5 Feb 4am
|
Diversions- A clearly signed diversion will be in place during all closures utilising local routes, suitable for all types of vehicles when full closures of the carriageway are in place.
Northbound traffic for Gatwick Airport will exit at Junction 10 and take the A2011 Crawley Avenue to the A23 London Road to reach Airport Way and access the North Terminal roundabout and follow the signposted route to the South Terminal.
Northbound traffic for the M25 will exit at Junction 10 and follow the A264 through Copthorne, turning left (northbound) onto the A22 at the traffic lights at Felbridge. Traffic will continue northbound on the A22 through New Chapel, Blindley Heath and South Godstone, reaching the M25 at the Junction 6 Godstone Interchange.